You have been reassigned to an existing project replacing the current project manager who has left the organization. You want to determine the quality goals and objectives for the project. What should you do
A Reach out to the team.
B Review the quality management plan.
C Review the project charter.
D Review the organizational process assets because they are standard operating procedures.
C::