Question: uestion 6 ( 1 point ) Listen A simple project listing of five activities, their predecessors and their respective time estimates are presented below: Activity
uestion point
Listen
A simple project listing of five activities, their predecessors and their respective time estimates are presented below:
Activity
Immediate Predecessor
Time in Days
A
None
B
A
C
A
D
B and C
E
D
Using the Single Time Estimate CPM procedure, what is the Early Start Time for the last activity in this project