Question: uestion 6 ( 1 point ) Listen A simple project listing of five activities, their predecessors and their respective time estimates are presented below: Activity

uestion 6(1 point)
Listen
A simple project listing of five activities, their predecessors and their respective time estimates are presented below:
Activity
Immediate Predecessor
Time in Days
A
None
3
B
A
2
C
A
1
D
B and C
3
E
D
4
Using the Single Time Estimate CPM procedure, what is the Early Start Time for the last activity in this project ?