Question: undefinednot precisely limited, determined, or distinguishedMore (Definitions, Synonyms, Translation) PROBLEM 10: T-3 T-6 T-4 Start E T-5 H T-7 Finish B T-5 PE T-6 From

undefinednot precisely limited, determined, or distinguishedMore (Definitions, Synonyms, Translation) PROBLEM 10: T-3 T-6 T-4 Start E T-5 H T-7 Finish B T-5 PE T-6 From the network diagram above, determine the critical path and the the project duration? Lets assume the completion of A is delayed by 2 days then what other activities are impacted? Now let's assume the completion of B is delayed by 2 days, then what will happen to the project