Question: Under a standard cost system, who is usually held responsible for the materials price variances? Select one: a . The engineering manager. b . The

Under a standard cost system, who is usually held responsible for the materials price variances?
Select one:
a. The engineering manager.
b. The production manager.
c. The purchasing manager.
d. The sales manager.