Question: Under field conditions, a saturated clay layer with a depth of H = 3 m resting on a non - permeable rock ( one -

Under field conditions, a saturated clay layer with a depth of H=3m resting on a non-permeable rock
(one-way drainage) requires 270 days to complete 70% of its primary consolidation. How long (in
minutes) will it take for a sample of the same clay with a height of H=25mm to achieve the same 70%
degree of consolidation under oedometer testing (laboratory) conditions?