Question: Under Normal time, if the earliest start ( ES ) time of activities F and G were 2 5 and 2 1 , what would

Under Normal time, if the earliest start (ES) time of activities F and G were 25 and 21, what would be the project duration? ____
____
A)28 days
B)26 days
C)24 days
D)23 days