Question: Under the current process layout, workers are allocated to the stations as shown here: Worker 1 : Steps 1 and 2 Worker 2 : Steps

Under the current process layout, workers are allocated to the stations as shown here:
Worker 1: Steps 1 and 2
Worker 2: Steps 3 and 4
Worker 3: Step 5
Worker 4: Step 6
Worker 5: Step 7
a. What is the bottleneck in this process?
b. What is the capacity of this assembly line, in finished units/hour?
c. What is the utilization of Worker 4?
d. What is the average labor utilization of the workers?