Question: Under the IRR decision model, a project should be accepted if the Blank _ _ _ _ _ _ . Multiple choice question. estimated IRR
Under the IRR decision model, a project should be accepted if the Blank
Multiple choice question.
estimated IRR of the project is greater than the company's discount rate
ratio of IRR to NPV is positive
IRR is greater than zero
estimated present value of future cash flows is positive, when discounted at the weightedaverage cost of capital