Question: Under the lot - for - lot ( L 4 L ) lot sizing technique as used in a MRP , we would expect which

Under the lot-for-lot (L4L) lot sizing technique as used in a MRP, we would expect which of the following?
Multiple Cholce
A just in time management philosophy.
Minimized carrying costs.
Minimized quality problems.
A consistent lag of supply behind demand.
Minimized set-up costs.
 Under the lot-for-lot (L4L) lot sizing technique as used in a