Question: Under the Precedence Diagramming Method, the Lag which occurs when a relationship between two tasks that can or must start at the same time is

Under the Precedence Diagramming Method, the Lag which occurs when a relationship between two tasks that can or must start at the same time is called: a) Finish-To-Start (FS) b) Start-To-Start (SS) c) Finish-To-Finish (FF) d) Start-To-Finish (SF)