Question: UNIT 1- PRACTICE MILESTONE 1 @ Download Practice Milestone PDF < 1 2 3 4 5 6 7 This is a practice Milestone India is
UNIT 1- PRACTICE MILESTONE 1 @ Download Practice Milestone PDF < 1 2 3 4 5 6 7 This is a practice Milestone India is a project manager at an advertising firm, in charge of developing a new ad campaign for a client. Today, she learned from her boss that the client wants the campaign completed next week instead of next month. Which of these would be an agile way for India to adapt to this UN unexpected event? 1.1 O Create a project plan around the new deadline and ask for help as needed. O Cut down on sleep and exercise to squeeze in more working hours. O Inform her boss that the client's request is simply not possible. O Hand management of this particular project over to someone else: SAVE & CONTINUE