Question: UNIT 3 - CHALLENGE 3 1 : Pro: What type of action would be taken when establishing rules during the kickoff meeting? a ) Describing

UNIT 3- CHALLENGE 31: Pro:
What type of action would be taken when establishing rules during the kickoff meeting?
a) Describing how team members should report project progress against the plan
b.) Sharing the expertise each team member brings to the project
c.) Explaining the project manager's expectations for team member involvement in team meetings
d) Reviewing the decision criteria that will be used during the project