Question: Unit 4 Assignment Chapter 1 2 Please follow the assignment ( Question Q 1 2 . 2 in the textbook Chapter 1 2 Section 1

Unit 4 Assignment Chapter 12
Please follow the assignment (Question Q12.2 in the textbook Chapter 12 Section 12.8 Practice Problems and Selected Solutions) and review the guidelines below for submitting your assignment:
12345678910
1
2 X
3 X
4 X
5 X
6 X
7 X
8 X
9 X X
10 X X
Table Summary: A table lists activity from 1 to 10.
Activity 12345678910
Time 54851124762
Table Summary: A table of ten activities and time required for each activity.
Q12.2(10 Activities) Consider the dependency matrix and the activity durations provided above.
Build a project graph, visually depicting the evolution of this project using AON. [12.2]
Find the critical path. What is the earliest time that the project can be completed? [12.4]
For each activity, compute the late start, the late completion, and the slack time. [12.5]
(Guidelines)
Submit as a Word.doc (or Excel)(Note: If I cannot view as a submission, it will get a zero grade. Links are not the same as an uploaded document, and links to a Google doc or other source does not always give me something I can grade and give feedback). Make sure to put your name on the document (title page).
Answer a) by completing an AON graph.
Answer b) by noting in writing the critical path and completing a table for each path and calculate critical path.
Answer c) by completing a table for each path and calculate slack. Table should include a list of each activity and contain the following headings: Duration, EST, ECT, LCT, LST, Slack. (Note: This table should support your answer for b).

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!