Question: (Unit 4) Schedules develop as the project moves from its early conceptual phase into the execution phase. Which type of schedule is often part of
(Unit 4) Schedules develop as the project moves from its early conceptual phase into the execution phase. Which type of schedule is often part of the contract and has detail regarding major events and dates such as the starting date and completion date? The project sponsor must approve any changes to this schedule and any changes must be made using a documented change process. O Gantt Detailed schedule Master schedule Conceptual schedule