Question: Unit 7 Assignment: PMB Due Date: Sunday by 11:59pm Total Points: 100 Instructions: Review the Control Account information, and determine the current status for each


Unit 7 Assignment: PMB Due Date: Sunday by 11:59pm Total Points: 100 Instructions: Review the Control Account information, and determine the current status for each of the work packages listed. Calculate the SV, CV, SPI, CPI, EAC, VAC, and TCPI for each of the following work packages: Work Package EV PV or EV or AC or SV SPI |EAC VAC TCPI Techniq BCWS BCWP ACWP ue 1.1.1.1.1. 50/50 $310 m $155 m $155 m Hull - Order Raw Steel 1.1.1.1.2. 50/50 $9 m $4.5 m $1m Hull - Order Polymer Material 1.2.1. % $4 m $3.7 m $4.1 m Final Certified complet Bow e Redesign 1.2.2.1 0/100 $ 1.2 m $1.2 m $1 mil Systems Engineering Planning- PMB Development 1.3.2. 0/100 $.5 m $.5 m $.3 m Project Management Planning - PMB development