Question: University Question 1 [ 2 0 marks ] Table 1 shows the schedule for a construction project that is intended to be completed in five
University
Question
marks
Table shows the schedule for a construction project that is intended to be completed in five months.
Table Project schedule and estimated costs
tableActivitytableEstimatedCosttablemonthtablemonthtablemonthtablemonthtablemonthABCDEF
After two and a half months, activities A and B are complete, activity C is complete, activity is complete, activity is complete, and activity has not been started yet. The actual project cost to date is $
Perform the earned value analysis to determine the following values: CV CPI, SPI, BAC, EAC, ETC, and VAC. Also, draw your conclusion about whether the project is over or under budget and whether it is ahead or behind schedule at this point. And explain what SPI and CPI indicate in this case.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock