Question: University Question 1 [ 2 0 marks ] Table 1 shows the schedule for a construction project that is intended to be completed in five

University
Question 1
[20 marks]
Table 1 shows the schedule for a construction project that is intended to be completed in five months.
Table 1 Project schedule and estimated costs
\table[[Activity,\table[[Estimated],[Cost]],\table[[month],[1]],\table[[month],[2]],\table[[month],[3]],\table[[month],[4]],\table[[month],[5]]],[A,1000,,,,,],[B,500,,,,,],[C,3000,,,,,],[D,2500,,,,,],[E,2200,,,,,],[F,2000,,,,,]]
After two and a half months, activities A and B are 100% complete, activity C is 80% complete, activity D is 30% complete, activity E is 20% complete, and activity F has not been started yet. The actual project cost to date is $7,000.
Perform the earned value analysis to determine the following values: EV,PV,AC,SV, CV, CPI, SPI, BAC, EAC, ETC, and VAC. Also, draw your conclusion about whether the project is over or under budget and whether it is ahead or behind schedule at this point. And explain what SPI and CPI indicate in this case.
 University Question 1 [20 marks] Table 1 shows the schedule for

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!