Question: : Update your risk register with the new information. Develop a decision tree with two alternatives: ( 1 ) accept the risk and continue construction,

: Update your risk register with the new information. Develop a decision tree with two alternatives:(1) accept the risk and continue construction, or (2) accelerate construction to avoid the risk. You have two states of nature, the storm causes damage 60% probability, and the storm does not cause damage. Use expected monetary value analysis for these two decisions and select the preferred alternative