### Preliminary Schedule
1. **Project Kick-off** - 1 day
2. **Market Research** - 5 days
3. **Content Planning** - 3 days
4. **Website Design** - 10 days
5. **Content Creation** - 8 days
6. **Website Development** - 15 days
7. **Testing** - 5 days
8. **Launch** - 1 day