Question: Upon receiving the CCD , what steps should GC take to preserve and pursue a claim for additional compensation? Group of answer choices Issue a
Upon receiving the CCD what steps should GC take to preserve and pursue a claim for additional compensation?
Group of answer choices
Issue a stop work notice until an agreement is reached and a change order, rather than construction change directive, is executed by all parties.
Notify the architect in writing of the disagreement over the CCD proceed with work, implement a procedure for tracking costs of the extra work, and initiate theclaims process.
Record a lien and file suit to foreclose the lien.
Obtain substitute collateral for the CCD and proceed with the work.