Question: URGENT HELP PLEASE - Following table provides tasks on an assembly line, along with their immediate predecessors and task times. Task Time (Minutes) Immed. Pred.

URGENT HELP PLEASE -

  1. Following table provides tasks on an assembly line, along with their immediate predecessors and task times.
Task Time (Minutes) Immed. Pred.
A 0.7 None
B 0.2 A
C 0.4 None
D 1.0 B
E 0.3 A
F 0.5 C
G 0.7 D,E,F
H 1.2 G

The cycle time is 1.3 minutes. Draw precedence diagram. Balance the line (assign all tasks) using the longest task time rule and fill out below table. Calculate the efficiency.

Following table provides tasks on an assembly line, along with their immediate predecessors and task times.

Task Time (Minutes) Immed. Pred.
A 0.7 None
B 0.2 A
C 0.4 None
D 1.0 B
E 0.3 A
F 0.5 C
G 0.7 D,E,F
H 1.2 G

The cycle time is 1.3 minutes. Draw precedence diagram. Balance the line (assign all tasks) using the longest task time rule and fill out below table. Calculate the efficiency.

Work station Eligible Task Task time Idle time

2. A decision tree is provided.

A. Calculate Expected value (EV) at every node. Show work.

B. What is the optimum decision and EV?

C. If your risk tolerance is $0, what is the best decision and EV?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!