Question: urgent Obor 17 in e cake baking unit five orders are to be processed in two machines one after the other The jobs are to

urgent Obor 17 in e cake baking unit five ordersurgent
Obor 17 in e cake baking unit five orders are to be processed in two machines one after the other The jobs are to be processed first on the mixing machine. Mtand later in the baking oven M2. The processing time in hours for each order on each machine is given below 3.00 Jobs A B D E M/CH question M (Mixing) 4 8 3 6 10 Mo (Oven) 6 3 7 2 Find the optimum sequence of the jobs that minimizes the total time required to complete them. Also calculate the total time for completing all the orders and the Idle time of the machines by using a Gantt chart

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!