Question: URGENT With the following samples, compute the average waiting time and the average turnaround time for the table below. 1 is highest priority, Note the
URGENT
With the following samples, compute the average waiting time and the average turnaround time for the table below. 1 is highest priority, Note the arrival times are not all zero. (8 marks)
| Process | Arrival time | Priority | CPU burst time |
| P1 | 0 | 4 | 12 |
| P2 | 1 | 2 | 9 |
| P3 | 2 | 1 | 3 |
- FCFS scheduling
- Preemptive SJF scheduling
- Non-preemptive priority scheduling
- Round Robin Scheduling with time quantum of 4
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock