Question: Usage per Parent Item Lead Time _(weeks) 1 2 B 2 3 3 D 4 5 E F 5 3 2 3 The end product

Usage per Parent Item Lead Time _(weeks) 1 2 B 2

Usage per Parent Item Lead Time _(weeks) 1 2 B 2 3 3 D 4 5 E F 5 3 2 3 The end product A is made from components B, and C. B is made from D, E, and F. If the company plans to build 10 of its A model. Assume that there are no beginning inventories. What is the gross requirement for component E? 10 40 80 100