Question: Use Constructive Cost Model (COCOMO) method to estimate software development projects was developed in the aerospace industry in the 1970s and represented an advancement in
Use Constructive Cost Model (COCOMO) method to estimate software development projects was developed in the aerospace industry in the 1970s and represented an advancement in the ability to estimate the effort required to develop software. There are 12,000 lines of code, and the values a, b, c, and d are taken from the following table:
| a | b | c | d |
| 2.5 | 1.10 | 2.5 | 0.36 |
What is the value of development time in months?
Group of answer choices
29.70
29,700
69,068.80
34.61