Question: Use critical path algorithm to create a priority list. Use the critical path algorithm to create a priority list for the digraph below, then schedule

Use critical path algorithm to create a priority list.

Use the critical path algorithm to create a priority list for the digraph below, then schedule the project with two processors. T1 (9) T4 (10) T7 (5) T2 (11) T5 (9) T8 (7) End T3 (12) T6 (6) T9 (5) Q Task 5 is done by Select an answer v |starting at time Task 6 is done by Select an answer v starting at time The finishing time for the schedule is