Use Earned Value to solve if your project is really going the way you planned.
1. Your project has a total budget of 300.000 TL. You check your records and find that youve spent 175.000 TL so far. The team has completed 40% of the project work, but when you check the schedule it says that they should have completed 50% of the work. Calculate Earned Value numbers PV, EV, SV, CV, SPI, CPI.