Question: Use Excel to complete the MRP explosion for Items B, C, and D based on the information collected from the Operations, Engineering, and Purchasing managers.

Use Excel to complete the MRP explosion for Items B, C, and D based on the information collected from the Operations, Engineering, and Purchasing managers.

Point: 2.5% of total grade or 25 points out of 1000.

Due on 4/20 midnight

Information from Operations: The MPS start quantities for product A calls for the assembly department to begin final assembly according to the following schedule:

Finished Item A 1 2 3 4 5 6 7 8 9 10
MPS Start for Item A 0 100 0 200 0 120 180 60 0 0
  • Information from Engineering

Finished Goods A uses 1 unit of component B and 2 units of sub-assembly C.

One unit of sub-assembly C uses 2 units of component D.

The lead times for B, C, and D are 1, 2, and 1, respectively.

  • Information from Purchasing Manager
INVENTORY RECORD DATA
Item
Data Category B C D
Lot-sizing rule FOQ = 50 units Lot-for-Lot POQ = 3
Lead time 1 week 2 weeks 1 week
Scheduled receipts None 200 (week 1) None
Beginning (on-hand) inventory 20 0 425

Lot-sizing Rule

FOQ = 50: Fixed Order Quantity = The order must be multiple of 50

Lot-for-Lot: The order can be any amount

POQ = 3: Periodic order quantity (POQ) = The order needs to cover the gross requirements of coming 3 time periods

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!

Q:

\f