Question: Use Johnson's rule to determine the optimal processing sequence for the jobs listed in the following table. Processing Time (mins) JOB ST1 ST2 A 30
Use Johnson's rule to determine the optimal processing sequence for the jobs listed in the following table.
| Processing Time (mins) | ||
| JOB | ST1 | ST2 |
| A | 30 | 12 |
| B | 8 | 16 |
| C | 10 | 9 |
| D | 14 | 7 |
| E | 5 | 4 |
| F | 15 | 5 |
Please write the optimal processing sequence for the six jobs