Use Johnson's rule to determine the optimal sequencing for the seven jobs to be processed onQuestion: Use Johnson's rule to determine the optimal sequencing for the five jobs to be processed on two machines in a fixed order Machine before Machine The processing times in hours are given in the table below.a What is the optimal sequence?b What is the total flow time for this sequence? c which job is first to be scheduled? is it scheduled to be the first job or the last? explain. JobMachine Machine ABCDEFG