Question: Use Johnson's rule to find the optimum sequence for processing the jobs shown through two work centres.Illustrate the throughput time and idle time at the
Use Johnson's rule to find the optimum sequence for processing the jobs shown through two work centres.Illustrate the throughput time and idle time at the two work centres by constructing a time phased chart. Time at each centres are in hours.
| Job | Work centre 1 | Work centre 2 |
| A | 6 | 12 |
| B | 3 | 7 |
| C | 18 | 9 |
| D | 15 | 14 |
| E | 16 | 8 |
| F | 10 | 15 |