Question: Use Microsoft Project to develop the early start schedule for the following product marketing project, to begin January 1 st , 2 0 2 4

Use Microsoft Project to develop the early start schedule for the following product marketing
project, to begin January 1st,2024.
Identifier Activity Predecessor Duration (weeks)
1 File for patent None 4
2 Obtain patent approval 10
3 Prototype design None 8
4 Prototype safety check 33
5 Prototype approval 40
6 Local market survey 56
7 Redesign product 2,612
8 Safety check of redesign 73
9 Local test 81
10 National market survey 910
11 Production design 98
12 Product liability analysis 94
13 Approve product 10,11,120
14 Produce product 131
15 Safety test product 146
16 Approve production output 150
17 Develop advertising campaign 2,612
18 Begin advertising 10,173
19 Deliver product 161
Write a report evaluating the project, to include critical activities and expected completion
time.
Identify Early Start, Early Finish, and Total Slack for each activity, as well as a Gantt chart
(you can cut and paste from MS Project).

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!