Question: USE SOLVER ON EXCEL TAKE SCREENSHOTS A small job shop needs to schedule six jobs. The due date and days needed to complete each job
USE SOLVER ON EXCEL
TAKE SCREENSHOTS
A small job shop needs to schedule six jobs. The due date and days needed to complete each job are given below. In what order should the jobs be scheduled to minimize the total days the jobs are late? JobT Processing Time Due Date Measured From Today 32 29 8 18 C) (i 21 37 28 4 6 A small job shop needs to schedule six jobs. The due date and days needed to complete each job are given below. In what order should the jobs be scheduled to minimize the total days the jobs are late? JobT Processing Time Due Date Measured From Today 32 29 8 18 C) (i 21 37 28 4 6