Question: Use the attached excel file to Create a MS Project File. when complete attach the file below. The project name is Mobile Reporting System. The

Use the attached excel file to Create a MS Project File. when complete attach the file below. The project name is Mobile Reporting System. The summary tasks/deliverables are:

  1. Performance Requirements
  2. Software
  3. Hardware
  4. Prototype

Show the project start date to be Sep 14, 2023.

Create a MS Project file that properly depicts the following:

  1. WBS Elements to the 3d level, with the proper indentionumbering system.
  2. Duration for all levels
  3. Start Finish Dates
  4. Predecessors
  5. Critical PathUse the attached excel file to Create a MS Project File. when

Task Name Mobile Reporting system Performance Requirements Interview Users Define Requirements Software Design Logic Design Database Code A code B Hardwaree Purchase Software Assemble Hardware Prototype Integrate SWHW Test Duration 7 1 3 [] 7 2 3 1 Task Name Mobile Reporting system Performance Requirements Interview Users Define Requirements Software Design Logic Design Database Code A code B Hardwaree Purchase Software Assemble Hardware Prototype Integrate SWHW Test Duration 7 1 3 [] 7 2 3 1

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!