Question: Use the below info to answer the questions. The time units are weeks. If the CT is equal to the NT, the activity cannot be

Use the below info to answer the questions. The time units are weeks. If the CT is equal to the NT, the activity cannot be crashed.

ACTIVITY IMMEDIATE PREDECESSOR(S) NORMAL TIME (NT) CRASH TIME (CT) NORMAL COST (NC) CRASH COST (CC)
A 3 3 $10 $10
B A 4 1 $2 $5
C A 7 5 $5 $9
D A 6 5 $3 $8
E B, C, D 8 5 $8 $62

a. If you want to crash one week, what activity/activities should be crashed? If multiple activities need to be crashed simultaneously, enter them in uppercase and in alphabetical order with a space between them, for example, A B, not AB, B A, A-B, etc.

b. If you want to crash a second week, what activity/activities should be crashed? If multiple activities need to be crashed simultaneously, enter them in uppercase and in alphabetical order with a space between them, for example, A B, not AB, B A, A-B, etc.

c. If you want to crash a third week, what activity/activities should be crashed? If multiple activities need to be crashed simultaneously, enter them in uppercase and in alphabetical order with a space between them, for example, A B, not AB, B A, A-B, etc.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!