Question: Use the data given below for all questions in this scenario. Your company has just received an order from a good customer for a specially

Use the data given below for all questions in this scenario.

Your company has just received an order from a good customer for a specially designed electric motor. The data on activity times and activity precedent relationships are given in the table below.

Activity Time (days) Immediate Predecessor(s)
A 4 None
B 7 None
C 5 None
D 6 A
E 3 B
F 11 C
G 4 D, E
H 3 F, G

Draw the project network diagram and answer the following questions.

A- The critical path is (only select one option):

A-D-G

C-F-H

C-F-G-H

B-E-G-H

B- How long will the project take to complete (in days)?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!