Question: Use the data given below for all questions in this scenario. Your company has just received an order from a good customer for a specially
Use the data given below for all questions in this scenario.
Your company has just received an order from a good customer for a specially designed electric motor. The data on activity times and activity precedent relationships are given in the table below.
| Activity | Time (days) | Immediate Predecessor(s) |
| A | 4 | None |
| B | 7 | None |
| C | 5 | None |
| D | 6 | A |
| E | 3 | B |
| F | 11 | C |
| G | 4 | D, E |
| H | 3 | F, G |
Draw the project network diagram and answer the following questions.
A- The critical path is (only select one option):
| A-D-G | ||
| C-F-H | ||
| C-F-G-H | ||
| B-E-G-H |
B- How long will the project take to complete (in days)?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts