Question: Use the data given in the following table and the relationships between activities shown in the Activity on Node (AON) network. Find the project duration
Use the data given in the following table and the relationships between activities shown in the Activity on Node (AON) network. Find the project duration (earliest completion time of the project.
| Activity | A | B | C | D | E | F | G |
| Time (days) | 5 | 6 | 9 | 4 | 9 | 3 | 4 |
Group of answer choices
21
22
25
28
31