Question: Use the data given in the following table and the relationships between activities shown in the Activity on Node (AON) network. Find the project duration

Use the data given in the following table and the relationships between activities shown in the Activity on Node (AON) network. Find the project duration (earliest completion time of the project.

Activity A B C D E F G
Time (days) 5 6 9 4 9 3 4

Group of answer choices

21

22

25

28

31