Question: Use the data in the following table to identify the critical path, project completion time, and slack for each activity. Activity Time Predecessors 1. High
Use the data in the following table to identify the critical path, project completion time, and slack for each activity.
|
Activity |
Time |
Predecessors |
| 1. High level analysis | 5 days | None |
| 2. Selection of hardware platform | 1 day | 1 |
| 3. Installation and commissioning of hardware | 14 days | 2 |
| 4. Detailed analysis of core modules | 14 days | 1 |
| 5. Detailed analysis of supporting utilities | 14 days | 3,4 |
| 6. Programming of core modules | 28 days | 3,4 |
| 7. Programming of supporting modules | 28 days | 5 |
| 8. Core module training | 1 day | 6 |
| 9.Development of management reporting | 22 days | 5 |
| 10.Detailed training and documentation | 14 days | 7,8,9 |
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock