Question: Use the data in the following table to identify the critical path, project completion time, and slack for each activity. Activity Time Predecessors 1. High

Use the data in the following table to identify the critical path, project completion time, and slack for each activity.

Activity

Time

Predecessors

1. High level analysis

5 days

None

2. Selection of hardware platform

1 day

1

3. Installation and commissioning of hardware

14 days

2

4. Detailed analysis of core modules

14 days

1

5. Detailed analysis of supporting utilities

14 days

3,4

6. Programming of core modules

28 days

3,4

7. Programming of supporting modules

28 days

5

8. Core module training

1 day

6

9.Development of management reporting

22 days

5

10.Detailed training and documentation

14 days

7,8,9

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!