Question: Use the data provided below to create a hand drawn or computer-generated AON network diagram. Calculate Forward Pass, Backward Pass, Slack Time and Critical Path.

Use the data provided below to create a hand drawn or computer-generated AON network diagram. Calculate Forward Pass, Backward Pass, Slack Time and Critical Path. Clearly identify your critical path. If you are submitting a hand drawn document, please sign and print your name to authenticate.

activity ID Preceding Activity Duration Maximum Crash Time Slope

A

NONE 3 1 $20
B A 5 2 $60
C A 3 1 $40
D A 10 0 0
E B 6 3 $50
F
G

C

D,F,F

7

5

3

1

$100

$70

Step 2: You have only 16 days to complete this project. What is the least cost solution to achieve completion in 16 days? Redraw a second AON network diagram showing completion of the network in 16 days and calculate Forward Pass, Backward Pass, Slack Time and Critical Path. Clearly identify your critical path. If you are submitting a hand drawn document, please sign and print your name to authenticate. Step 3: What is the least cost increase to achieve the 16-day duration? Please write out your calculations (Show your calculations to arrive at the least cost to increase to complete in 16 days)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!