Question: Use the EDD (Earliest due date ) rule to sequence the following jobs: Job Work time (days) Due date (days) 19 20 B 10 25

Use the EDD (Earliest due date ) rule to sequence

Use the EDD (Earliest due date ) rule to sequence the following jobs: Job Work time (days) Due date (days) 19 20 B 10 25 12 30 D 7 8 6 12 Select one: 1 A, C, B, D, E 2. E, D, B, C, A 3. D, E, A, B, C 4. A B, C, D, E