Question: Use the following 9 - Node diagram information to reduce the building schedule by 7 working days in the most economical manner. Contractor Days Offered

Use the following 9-Node diagram information to reduce the building schedule by 7 working days in the most economical manner.
Contractor Days Offered Days Used Total $$$ Costs
SUB A 3 days @ $250
SUB A 1 days @ $800
SUB B 2 days @ $500
SUB C 2 days @ $300
SUB C 2 days @ $600
SUB D None
SUB E 4 days @ 300
SUB F 3 days @ 400
SUB F 2 days @ 700
Total Costs $
36. After the buy-down in Q 35, how many tasks are now critical? 1 Point
a.3
b.4
c.5
d. All 6Use the following diagram to solve the schedule crash. Blanks are 1 point each
Use the following 9-Node diagram information to reduce the building schedule by 7 working
days in the most economical manner.
After the buy-down in Q 35, how many tasks are now critical?
Use the following 9 - Node diagram information to

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!