Question: Use the following data for Questions 5 and 6.Note: All times are in weeks Normal timeCrash timeNormal CostCrash CostCrash cost/pdCrash by Crashing cost Project 4228
Use the following data for Questions 5 and 6.Note: All times are in weeks
Normal timeCrash timeNormal CostCrash CostCrash cost/pdCrash by Crashing cost
Project 4228
A22200200000
B53450550502100
C84360720904360
D1288601000354140
E424004502500
F86720820502100
G931500190066.672133.33
H1510164522451202240
I623426427500
J94640800325160
K12711501350405200
L5424030060160
TOTALS 8507 1493.33
Project timePeriod costCumulative cost ABCDEFGHIJKL
4200
415050 1
4050100 2
3960160 2 1
3867227 2 1 1 1
3767294 2 2 2 1
3667361 2 3 3 1
3567428 2 4 4 1
3472500 2 4 511
33130630 214 521
32130760 224 531
31130890 234 541
301301020 244 551
29236.671256.67 244 111 551
28236.671493.33 244 222 551
1)If the project has to be completed in 35 weeks, which activities should be crashed and for how long?
A.B for two weeks, D for three weeks, J for three weeks, and L for one week
B.B for two weeks, D for four weeks, J for four weeks, and L for one week
C.B for two weeks, D for four weeks, J for five weeks, K for one week and L for one week
D.No activities need to be crashed
2)Your company earns a bonus of $145 per week that the project is completely early.What is your recommendation regarding completing the project early?
A.Do not attempt to complete the project early
B.Attempt to complete the project in 40 weeks
C.Attempt to complete the project in 30 weeks
D.Attempt to complete the project in 28 weeks
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts