Question: Use the following data for Questions 5 and 6.Note: All times are in weeks Normal timeCrash timeNormal CostCrash CostCrash cost/pdCrash by Crashing cost Project 4228

Use the following data for Questions 5 and 6.Note: All times are in weeks

Normal timeCrash timeNormal CostCrash CostCrash cost/pdCrash by Crashing cost

Project 4228

A22200200000

B53450550502100

C84360720904360

D1288601000354140

E424004502500

F86720820502100

G931500190066.672133.33

H1510164522451202240

I623426427500

J94640800325160

K12711501350405200

L5424030060160

TOTALS 8507 1493.33

Project timePeriod costCumulative cost ABCDEFGHIJKL

4200

415050 1

4050100 2

3960160 2 1

3867227 2 1 1 1

3767294 2 2 2 1

3667361 2 3 3 1

3567428 2 4 4 1

3472500 2 4 511

33130630 214 521

32130760 224 531

31130890 234 541

301301020 244 551

29236.671256.67 244 111 551

28236.671493.33 244 222 551

1)If the project has to be completed in 35 weeks, which activities should be crashed and for how long?

A.B for two weeks, D for three weeks, J for three weeks, and L for one week

B.B for two weeks, D for four weeks, J for four weeks, and L for one week

C.B for two weeks, D for four weeks, J for five weeks, K for one week and L for one week

D.No activities need to be crashed

2)Your company earns a bonus of $145 per week that the project is completely early.What is your recommendation regarding completing the project early?

A.Do not attempt to complete the project early

B.Attempt to complete the project in 40 weeks

C.Attempt to complete the project in 30 weeks

D.Attempt to complete the project in 28 weeks

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Mathematics Questions!