Question: Use the following data for the next two problems The following table contains information regarding jobs that are to be scheduled through one machine. Assume

Use the following data for the next two problems

The following table contains information regarding jobs that are to be scheduled through one machine. Assume jobs are listed in order of arrival (i.e., A, then B, then C, etc.).

JOB PROCESSING TIME (DAYS) DUE DATE
A 5 23
B 12 21
C 2 18
D 9 17
E 10 15
F 4 6
G 7 13

(Round your answers to Part e to 1 decimal place.

Using a first-come, first-served (FCFS) schedule, what is the flow time for F?