Use the following data to answer questions
| Activity | Optimistic time | Most likely time | Pessimistic time |
| A | 4 | 8 | 14 |
| B | 1 | 2 | 17 |
| C | 8 | 15 | 18 |
| D | 6 | 7 | 10 |
| E | 4 | 9 | 14 |
- What is the expected time for activity C (round to closest integer)?
- 12
- 13
- 14
- 15
- If activities A, C and E are on the critical path, what is the project variance?
- 8.33
- 10.88
- 30.67
- 2.31