Question: Use the following data to answer questions Activity Optimistic time Most likely time Pessimistic time A 4 8 14 B 1 2 17 C 8

Use the following data to answer questions

Activity

Optimistic time

Most likely time

Pessimistic time

A

4

8

14

B

1

2

17

C

8

15

18

D

6

7

10

E

4

9

14

  1. What is the expected time for activity C (round to closest integer)?
    1. 12
    2. 13
    3. 14
    4. 15

  1. If activities A, C and E are on the critical path, what is the project variance?
  1. 8.33
  2. 10.88
  3. 30.67
  4. 2.31

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!