Question: Use the following data to find the direct labor efficiency variance. Direct labor standard (4.0 hrs.@ $ 7/hr.) $28per finished unit Actual hours worked per
| Use the following data to find the direct labor efficiency variance. |
| Direct labor standard (4.0 hrs.@ $ 7/hr.) | $28per finished unit |
| Actual hours worked per unit | 3.5 hrs |
| Actual units produced | 4,700 units |
| Actual rate per hour | $7.25 |
Group of answer choices
$4,113 unfavorable
$18,800 unfavorable
$18,800 favorable
$16,450 favorable
$4,112 favorable