Question: Use the following differential leveling survey field notes to answer the next five ( 5 ) questions. Reduce the field notes, do the arithmetic check

Use the following differential leveling survey field notes to answer the next five (5) questions. Reduce the field notes, do the arithmetic check and the accuracy check.
\table[[STA,BS,HI,FS,IFS,ELEV],[,,,,,],[BM 67,2.548,,,,68.881],[,,,,,],[TP 1,1.226,,0.966,,],[,,,,,],[TP 2,1.627,,1.691,,],[,,,,,],[0+110,,,,1.52,],[,,,,,],[0+120,,,,1.48,],[,,,,,],[0+130,,,,1.36,],[,,,,,],[TP 3,0.588,,2.414,,],[,,,,,],[BM 67,,,0.933,,]]
Length of run =1650 meters
Question 13
2 pts
Determine the closure error in millimeters (accurate to the nearest millimeter) when the survey ends at BM67.
Do not include units in your answer
Use the following differential leveling survey

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!