Question: Use the following information Activity Immediate Predecessor(s A B C D F G H I J K L none none A, B A B

Use the following information Activity Immediate Predecessor(s A B C D F G H I J K L none none A, B A B C, D, 2. Calculate the critical path and the project completion time for the project. 

Use the following information Activity Immediate Predecessor(s A B C D F G H I J K L none none A, B A B C, D, E F F F H. I J K Normal Time (weeks) 10 4 6 7 14 3 4 2 5 2 5 10 Normal Cost (S) 16,000 6,000 12,000 7,000 28,000 4.500 7,200 5,000 15,000 7,000 10,000 24,000 Crash Time (weeks) 8 3 3 5 12 3 3 2 4 2 4 10 Crash Cost ($) 20.000 9,000 24,000 10,000 34,000 4,500 9,000 5,000 18,000 7,000 11,000 24,000 2. Calculate the critical path and the project completion time for the project.

Step by Step Solution

3.45 Rating (152 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Here are the detailed stepbystep calculations 1 Activity L ES 0 given as it is the last activity Nor... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!