Question: Use the following information below. The information below reports a project's activity times (in days) and precedence relationships. Activity Time (days) Predecessors ____________________________________________ A 7
Use the following information below. The information below reports a project's activity times (in days) and precedence relationships.
Activity Time (days) Predecessors
____________________________________________
A 7 NONE
B 4 NONE
C 11 A
D 5 A,B
E 6 B
F 10 C,D
G 6 B,F
H 4 E,F
What is your estimate of comple tion time for this project?
How many critical paths exist in this project?
What is the Earliest Start (ES) time for activity G?
What is the slack for activity E?