Question: Use the following information to compress one - time unit per move using the least - cost method. Reduce the schedule until you reach the
Use the following information to compress onetime unit per move using the leastcost method. Reduce the schedule until you reach the crash point of the network. For each move identify what activitys was crashed and the adjusted total cost.
Note: The correct normal project duration, critical path, and total direct cost are provided.
To compress from time period to time crash the following activitysYou may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer. Any boxes left with a question mark will be automatically graded as incorrect.
mathrmA
c
D
E
F
To compress from time period to time crash the following activitys: You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer. Any boxes left with a question mark will be automatically graded as incorrect.
A
D
mathrm~F
mathrm~F
mathrmG
mathrmH
What is the adjusted total cost at time period To compress from time period to time crash the following activitys: You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer. Any boxes left with a question mark will be automatically graded as incorrect.
mathrmA
C
D
mathrmE
mathrm~F
mathrmG
mathrmH
What is the adjusted total cost at time period
What is the crash point of the network? Hint To obtain crash point, crash the project as much as is possible. What is the adjusted total cost at time period
What is the crash point of the network? Hint To obtain crash point, crash the project as much as is possible.
What is the optimum costtime schedule for the project?
weeks
What is this cost?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
