Question: Use the following information to compress one - time unit per move using the least - cost method. Reduce the schedule until you reach the

Use the following information to compress one-time unit per move using the least-cost method. Reduce the schedule until you reach the crash point of the network. For each move identify what activity(s) was crashed and the adjusted total cost.
Note: The correct normal project duration, critical path, and total direct cost are provided.
To compress from time period 12 to time 11 crash the following activity(s)(You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer. Any boxes left with a question mark will be automatically graded as incorrect.)
\(\{\mathrm{A}\)
\(\{\)
\(? c \)
3 D
?E
3 F
To compress from time period 16 to time 15, crash the following activity(s): (You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer. Any boxes left with a question mark will be automatically graded as incorrect.)
3 A
\(\{\)
?
3 D
\(?\mathrm{~F}\)
\(?\mathrm{~F}\)
\(?\mathrm{G}\)
\(\{\mathrm{H}\)
\(?\)
What is the adjusted total cost at time period 15? To compress from time period 15 to time 14, crash the following activity(s): (You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer. Any boxes left with a question mark will be automatically graded as incorrect.)
\(\{\mathrm{A}\)
\(?\)
1 C
\(\{\) D
\(\{\mathrm{E}\)
\(?\mathrm{~F}\)
\(?\mathrm{G}\)
\(\{\mathrm{H}\)
\(?1\)
What is the adjusted total cost at time period 14?
What is the crash point of the network? (Hint. To obtain crash point, crash the project as much as is possible.) What is the adjusted total cost at time period \(14?\)
What is the crash point of the network? (Hint. To obtain crash point, crash the project as much as is possible.)
What is the optimum cost-time schedule for the project?
weeks
What is this cost?
 Use the following information to compress one-time unit per move using

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!