Question: Use the following information to create an earned value chart. Assume that you have completed three months of the project. The BAC was $200,000 for
Use the following information to create an earned value chart.
Assume that you have completed three months of the project.
The BAC was $200,000 for this six-month project.
PV = $120,000
EV = $100,000
AC = $90,000
Cost variance = EV-AC=$100,000 - $90,000 = $10,000
Schedule variance = EV-PV=$100,000-$120,000=($20,000)
CPI=EV/AC=$100,000/$90,000 =111% or 1.11
SPI=EV/PV=$100,000/$120,000=83% or .83
EAC=BAC/CPI=$200,000/1.11=$180,180
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
