Question: Use the following partially completed MRP record to answer the question. Item: XYZ Lot Size: periodic order quantity (POQ), with P = 2 ; Lead

Use the following partially completed MRP record to answer the question.

Item: XYZ Lot Size: periodic order quantity (POQ), with P = 2 ; Lead Time: 2 weeks

Date

1

2

3

4

5

6

7

8

Gross Requirements

20

30

50

40

20

Scheduled Receipts

50

Projected on Hand (Zero)

Planned Receipts

Planned Order Release

What are the quantities of planned order releases for item XYZ for the first six weeks (weeks 1, 2, 3, 4, 5, and 6)?